NEW QUESTION NO: 6
DRAG DROP
You are a project manager in an organization that is using Microsoft PPM for work management.
You have already accepted all status updates in the Approval Center, but you are still unable to see the updates in your project schedule.
You need to ensure that status updates are reflected in your project schedule.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
Select and Place:

Answer: 


NEW QUESTION NO: 7
Your organization is using Microsoft PPM to manage large projects. Within the Microsoft PPM environment, you use SharePoint sites with task lists to manage smaller projects. You turn on the Timesheets feature.
You must collect information about the time that resources spend on all projects.
You need to ensure that you can capture timesheet data from the existing SharePoint task lists.
Which two actions will achieve the goal? Each correct answer presents a complete solution.
A. Convert the SharePoint task lists into an enterprise project.
B. Use the Get Started with Project Web App web part to add existing SharePoint task lists to Project Center.
C. Activate the enterprise project features for the SharePoint sites.
D. In Project Center, add existing SharePoint task lists to PWA as a project.
E. In SharePoint, add existing SharePoint task lists to Project Center.
Answer: A,C
Explanation/Reference:
Explanation:

NEW QUESTION NO: 8
HOTSPOT
You are a project manager for an organization that is using Microsoft PPM to manage projects. Projects are staffed using the enterprise resource pool.
You assign a resource to a task and set the value of Work hours to 10. You assign no overtime hours.
For each of the following statements, select Yes if the statement is true. Otherwise, select No.
Hot Area:

Answer: 


NEW QUESTION NO: 9
Your organization is in the process of implementing Microsoft PPM.
You need to configure Microsoft PPM to ensure that project managers can choose the tracking method for each of their projects.
On the Task Settings and Display page, what should you do?
A. Set the tracking method to Free form.
B. Select the check box Force project managers to use the progress reporting method specified above for all projects.
C. Clear the check box Force project managers to use the progress reporting method specified above for all projects.
D. Set the tracking method to Percent of work complete.
Answer: A
Explanation/Reference:
Explanation:

NEW QUESTION NO: 10
HOTSPOT
You are a project manager and want to display key deliverables associated with your project. The tasks that produce the deliverables are already on the project schedule.
You need to ensure that the deliverables are visible on the project site.
For each of the following statements, select Yes if the statement is true. Otherwise, select No.
Hot Area:

Answer: 

Explanation/Reference:
References:
https://diegocampereira.com/2017/02/10/creating-deliverables-using-microsoft-project-professional-and- project-site/

NEW QUESTION NO: 11
DRAG DROP
You are a program manager who is using Microsoft PPM and Microsoft Project to manage an e-commerce portal development program.
The program is separated into individual projects that represent each area of development, so that each group can manage its own tasks while still having progress visibility at the program level.
You need to be able to manage the overall program as well as its associated individual projects within Project Center. This includes the project sites associated with both the program and the individual projects.
Each individual project site should be a subsite of the overall program project site.
You need to create the master program, the individual projects, and their associated project sites.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area, and arrange them in the correct order.
Select and Place:

Answer: 


NEW QUESTION NO: 12
HOTSPOT
A project that you manage begins to go over budget.
You need to reduce the scope of the project and retain a baseline record for all tasks.
For each of the following statements, select Yes if the statement is true. Otherwise, select No.
Hot Area:

Answer: 


NEW QUESTION NO: 13
You are a project manager using Microsoft PPM.
You need to create a new project that uses one of your company's templates.
What are two ways to achieve the goal? Each correct answer presents a complete solution.
A. From Microsoft Project, select Enterprise.
B. In Project Center, select New, and then select the desired enterprise project type.
C. In Resource Center, select New.
D. From Microsoft Project, select Featured.
Answer: A,B
Explanation/Reference:
Explanation:

NEW QUESTION NO: 14
DRAG DROP
You are a project manager in an organization that is using Microsoft PPM. You are managing a 12-month project. Resources have been working on the project for six months.
You need to determine how the project is tracking against the initial goals in terms of duration, work and cost.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area, and arrange them in the correct order.
Select and Place:

Answer: 

Explanation/Reference:
References:
https://support.office.com/en-us/article/Create-or-update-a-baseline-or-an-interim-plan-7E775482-AC84-
4F4A-BBD0-592F9AC91953

NEW QUESTION NO: 15
You are a project manager in an organization that uses Microsoft PPM. You create a proposal for a new project by entering values for the Name, Description, Proposed Cost, Proposed Benefits, and Sponsor Name properties.
The PMO must be able to approve all project proposals that have a proposed cost above a certain threshold value.
You need to use a project approval workflow.
Which three objects should use? Each correct answer presents part of the solution.
A. Project Departments
B. Enterprise Project types
C. Project Detail Pages
D. Project schedule templates
E. Phases and stages
Answer: B,C,E
Explanation/Reference:
Explanation:

NEW QUESTION NO: 16
DRAG DROP
You are the Microsoft PPM administrator for a large organization.
You need to ensure that line managers can delegate timesheet approvals to their team members.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area, and arrange them in the correct order.
Select and Place:

Answer: 

Explanation/Reference:
References:
https://technet.microsoft.com/en-us/library/cc197631.aspx