Valid PRINCE2-Foundation Dumps shared by Examslabs for Helping Passing PRINCE2-Foundation Exam! Examslabs now offer the newest PRINCE2-Foundation exam dumps, the Examslabs PRINCE2-Foundation exam questions have been updated and answers have been corrected get the newest Examslabs PRINCE2-Foundation dumps with Test Engine here: http://https://www.examslabs.com/PRINCE2/PRINCE2-Certification/best-PRINCE2-Foundation-exam-dumps.html (300 Q&As Dumps, 30%OFF Special Discount: bmzblwH7 )


NEW QUESTION NO: 7
Which is an objective of the Starting up a Project process?
A. Identify who will be responsible for creating the Project Plan
B. Agree how the project will be monitored and controlled after initiation
C. Authorize the Project Manager to proceed with the initiation stage
D. Agree how issues and changes will be identified, assessed and controlled
Answer: A

NEW QUESTION NO: 8
Which is a true statement about acceptance criteria?
A. Acceptance criteria are used to produce the customer's quality expectations
B. Acceptance criteria are less specific and precise than customer's quality expectations
C. Acceptance criteria should be agreed between the customer and the supplier
D. Once agreed, acceptance criteria CANNOT be changed
Answer: C

NEW QUESTION NO: 9
Which is an objective of the Closing a Project process?
A. Review and approve the plan for project closure
B. Create a Benefits Review Plan
C. Review the performance of the project against its baseline
D. Perform any post-project reviews
Answer: C

NEW QUESTION NO: 10
What plan is created, and submitted for approval, during the Managing a Stage Boundary process?
A. Benefits Review Plan
B. Stage Plan
C. Project Plan
D. Team Plan
Answer: B

NEW QUESTION NO: 11
Which of the following statements about the Project Initiation Documentation are true?
1. The Project Initiation Documentation is used to ensure that a sound basis exists before the Project Board authorizes a project.
2. The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project.
A. Neither 1 or 2 are true
B. Both 1 and 2 are true
C. Only 1 is true
D. Only 2 is true
Answer: B

NEW QUESTION NO: 12
Which two roles are linked by the Managing Product Delivery process?
A. Project Manager and Team Manager
B. Team Manager and external supplier
C. Project Board and Project Manager
D. Corporate or programme management and Project Board
Answer: A

NEW QUESTION NO: 13
Identify the missing word(s) in the following sentence. During a quality review meeting [ ? ] any identified defects.
A. an issue should be created for
B. the agreed actions should be recorded for
C. a solution should be designed for
D. the chair will approve the solution to
Answer: B

NEW QUESTION NO: 14
Which of the following statements about the Closing a Project process are true?
1. The Closing a Project process provides a fixed point for the receipt of completed Work Packages for the work performed in the final stage.
2. The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved.
A. Both 1 and 2 are true
B. Neither 1 or 2 are true
C. Only 2 is true
D. Only 1 is true
Answer: C

NEW QUESTION NO: 15
Which activity takes place within the Managing a Stage Boundary process?
A. Authorize a Stage Plan for the next stage
B. Produce Highlight Reports
C. Produce an Exception Plan
D. Take corrective action within the limits of a stage's tolerance
Answer: C

NEW QUESTION NO: 16
Which is a purpose of a Project Product Description?
A. Shows the dependencies between the project's products to aid planning
B. Provides a list of all the products to be delivered by the project
C. Records the costs and timescales for delivery of the project's final product
D. Defines what the project must deliver in order to gain acceptance
Answer: D

NEW QUESTION NO: 17
Which of the following can be done to control the size of the Project Board on a project that involves multiple users and suppliers?
A. Create multiple smaller Project Boards during the process of Starting up a Project, one for each of the project's stages.
B. Create a separate Project Board to manage the supplier elements of the project
C. Appoint corporate quality assurance to perform the Project Assurance role for all members of the Project Board
D. Create user and supplier groups
Answer: D