NEW QUESTION NO: 5
When scheduling the Update Project Performance Data process to run on a periodic basis, which summarization method would you select? (Choose the best answer.)
A. Bulk
B. Detail
C. Incremental
D. Summary
Answer: A
Explanation/Reference:
Reference https://docs.oracle.com/cloud/farel10/projectcs_gs/OAPJS/OAPJS1058184.htm#OAPJS177676
NEW QUESTION NO: 6
You are managing a project based on a Waterfall model. You define a project and a project plan in Oracle Project Portfolio Management with tasks and subtasks applicable to each of the phases of the project:
Initiation, Discovery, Design, Build, Test, and Deploy. As a project manager, you want to define deliverables for your project requirements that are elucidated during the Discovery phase of your project.
You now want to understand how the inheritance between requirements, tasks, and deliverables works.
Identify the two correct statements in this respect. (Choose two.)
A. You associate a deliverable with a task independent of associating a requirement with a task.
B. The association of a deliverable with a task is dependent on associating a requirement with a task.
C. A deliverable associated with a requirement is automatically associated with the tasks created for that requirement.
D. A deliverable associated with a requirement is not automatically associated with the tasks created for that requirement.
Answer: A,B
NEW QUESTION NO: 7
Identify the three contract attributes from Project Performance Data that are used in Project Performance dashboard regions. (Choose three.)
A. Expenditure Type
B. Projects
C. Contract Line
D. Contract Header
E. Task
Answer: A,C,E
Explanation/Reference:
Reference https://docs.oracle.com/cloud/farel9/projectcs_gs/FAUAR/F1537947AN10251.htm
NEW QUESTION NO: 8
When implementing Project Performance Reporting, your customer has the following requirements:
Every time a project cost is greater than or equal to a threshold, then the project should be shown as

critical.
As long as a project cost is less than the threshold, the project should be shown as on-track.

Which threshold level rule is ideal for this kind of KPI definition? (Choose the best answer.)
A. single threshold level range
B. multiple threshold level value
C. single threshold level value
D. multiple threshold levels
Answer: C
NEW QUESTION NO: 9
You are set up as a Follower in Manage Tasks. Which two abilities can you accomplish? (Choose two.)
A. Enter progress for tasks.
B. Receive email notifications about changes that team members make to a task.
C. View task details and the task activity stream.
D. Edit task details.
Answer: B,C
Explanation/Reference:
Reference https://docs.oracle.com/cd/E48434_01/fusionapps.1118/e49889/F1122098AN1340E.htm
NEW QUESTION NO: 10
Your customer wants additional project information for detailed account balance maintenance, reconciliation, and reporting. Identify the configuration in subledger accounting that can be set up to fulfill this requirement. (Choose the best answer.)
A. Accounting Method
B. Journal Rules
C. Supporting References
D. Accounting Rule
E. Mapping Sets
Answer: C
Explanation/Reference:
Reference https://docs.oracle.com/cloud/latest/projectcs_gs/OAPFM/
OAPFM1125357.htm#OAPFM1125357
NEW QUESTION NO: 11
Identify the attribute of a project type that determines if expenditure items are billable, and the amount type to be used as the basis for transfer pricing. (Choose the best answer.)
A. work type
B. event type
C. cost type
D. expenditure type
Answer: A
Explanation/Reference:
Reference https://docs.oracle.com/cloud/latest/projectcs_gs/OAPFM/
OAPFM1125361.htm#OAPFM1125277 (what's a work type?)
NEW QUESTION NO: 12
Identify two correct role templates available on the Oracle Entitlement Server to generate roles for Project Organization Security. (Choose two.)
A. Project Manager Template for Project Organization Security
B. Project Administrator Template for Project Organization Security
C. Project Creator Template for Project Organization Security
D. Project Accountant Template for Project Organization Security
E. Project Billing Specialist Template for Project Organization Security
Answer: A,D
Explanation/Reference:
Reference https://docs.oracle.com/cloud/latest/common/FASER/FASER2406048.htm#FASER2406048
NEW QUESTION NO: 13
You have defined two expenditure types but they are not available for selection when you enter an expenditure batch. Identify the reason for this problem. (Choose the best answer.)
A. The two expenditure types are not assigned to the reference data set that is assigned to the project- owning organization in which the transaction is performed.
B. The two expenditure types are not assigned to the reference data set that is assigned to the project expenditure organization in which the transaction is performed.
C. The two expenditure types are not assigned to the reference data set that is assigned to the project unit in which the transaction is performed.
D. The two expenditure types are not assigned to the reference data set that is assigned to the business unit in which the transaction is performed.
Answer: B
NEW QUESTION NO: 14
A consulting services company is currently working on a business transformation project for your client, which spans multiple years. At the first period close, the consulting services company has recognized revenue and the accounting entry created is:
Dr Unbilled Receivables 40,000
Cr Revenue 40,000
At the end of the period, the client is sent an associated bill. What would be the corresponding invoice accounting entry? (Choose the best answer.)
A. Dr Unearned Revenue 40,000
Cr Revenue 40,000
B. Dr Unearned Revenue 40,000
Cr Accounts Receivables 40,000
C. Dr Accounts Receivables 40,000
Cr Unbilled Receivables 40,000
D. Dr Accounts Receivables 40,000
Cr Revenue 40,000
Answer: D
NEW QUESTION NO: 15
You recently made some changes to a project contract and the current status of the contract is Under Amendment. Identify the correct sequence of activities that can take place on that contract. (Choose the best answer.)
A. On Hold > Pending Acceptance > Active
B. On Hold > Pending Approval > Active
C. Pending Approval > Pending Acceptance > Active
D. Pending Acceptance > Pending Approval > Active
Answer: C
Explanation/Reference:
Reference https://docs.oracle.com/cloud/latest/common/FASCC/FASCC1124283.htm