C2010-591 Free Dumps Study Materials
Question 14: All change managers at a company need to track if the percentage of changes
implemented with
approval across a date range is higher then 90%. Which IBM SmartCloud Control Desk
functionality can
create and display the necessary Key Performance Indicator (KPI)?
A. The required KPI is already available which provides a graph of the percentage of
changes
implemented with approval by status.
B. A result set should be configured on the Start Center of the Change Manager role
containing a query on
the closed changes for a specific date range.
C. A standard report is already available which uses Start Date and End Date input
parameters to provide
a report with a bar chart of the percentage of changes implemented with and without
approval by status.
D. A custom KPI should be configured to display the percentage of changes implemented
with approval
by status, using Start Date and End Date input parameters, which then has to be configured
in a KPI
graph portlet on the dashboard of the Change Manager role.
Correct Answer: C