C2180-189 Free Dumps Study Materials
Question 8: A BPM analyst is creating a process model for requesting a renovation permit. The BPM
analyst is using the following description of the first activity:
"One of our municipal office clerks receives a paper permit application from the local resident, an
applicant. The clerk first looks up the resident's name and address in our system, then enters the
information from the paper application into the system, and assigns a temporary permit number to
the application. When the application entry is complete, the clerk sends it to a manager to assign it
to an adjudicator."
Which name should the BPM analyst use for the first task that accurately describes the activity and
follows recommended naming conventions?
A. Application Entry
B. Create Application
C. Clerk Receive and Enter Application
D. Lookup name, create application, assign number, and send it to the manager
Correct Answer: B