Question 1: As a type of measurement error, Linearity describes a change in accuracy through the
expected operating range of the measurement instrument.
A. True
B. False
Correct Answer: A
7. The purpose of a Process Map is to identify the complexity of the process and to assist in
identifying critical steps in the process.
A. True
B. False
Correct Answer: A
8. The generation of a Regression Equation is justified when we _____________. (Note: There
are 4 correct answers).
A. Expect the relationship to be Linear between the output and inputs
B. Know that there is a non-linear relationship between output and input(s)
C. Need to understand how to control a process output by controlling the input(s)
D. Experience several process defects and have no other way to fix hem
E. When it is very expensive or too late to measure the output
Correct Answer: A,C,D,E
9. The following Business Case is constructed properly.
"In business unit A there are too many flashlight returns and flashlight sales have decreased by 25
percent."
A. True
B. False
Correct Answer: B
10. The Empirical Rule is important because it provides an estimate of the probability of an event
occurring depending on the Standard Deviation from the Mean.
A. True
B. False
Correct Answer: A
11. Fractional Factorial designs for an experimental approach are used when ____________
about the multiple metric interaction in a process.
A. Much is known
B. Little is known
C. We don't care
D. Data exists
Correct Answer: B
12. Lean had its origins in the development and practice of the ___________ Production System.
A. Honda
B. Toyota
C. Ford
D. Motorola
Correct Answer: B
13. In the late 1980's William Smith coined the name Six Sigma for a methodology that had its
origins at __________________ for quality related work being done there.
A. Honeywell
B. Allied Signal
C. General Electric
D. Motorola
Correct Answer: D
14. Which of these statements describe an undesirable situation when implementing SPC? (Note:
There are 2 correct answers).
A. The lower Control Limit for the R chart is equal to zero
B. The Control Limits are wider than the customer specification limits
C. A process is in Statistical Control before implementation of SPC
D. Attempt to use SPC for tracking transaction times at a warehouse
E. Indication of the specification limits on the Control Chart
Correct Answer: B,E
15. As part of a Visual Factory plan Kanban cards are created and utilized to identify areas in
need of cleaning and organization.
A. True
B. False
Correct Answer: B
16. The ____________ is important because it provides an estimate of the probability of an
event occurring depending on the Standard Deviation from the Mean.
A. Shewhart Principle
B. Pareto Rule
C. Mean/Mode Spread
D. Empirical Rule
Correct Answer: D