In modern society, Microsoft 070-177 certificate has an important impact on your future job, your promotion and salary increase. Also it can make a great deal of difference in your career.
Here, BraindumpsQA's 070-177 exam materials will help you pass your Microsoft 070-177 certification exam and get Microsoft certification certificate. Our exam materials are written to the highest standards of technical accuracy. And the 070-177 exam questions and answers are edited by experienced IT experts and have a 99.9% of hit rate.
BraindumpsQA provides you with the most excellent and latest 070-177 PDF Version & Software version exam dumps. The Software version exam material is a test engine that simulates the exam in a real exam environment, which can help you test your level of knowledge about 070-177 exam.
If you have no good idea to prepare for Microsoft 070-177 exam, BraindumpsQA will be your best choice. Our 070-177 exam questions and answers are the most accurate and almost contain all knowledge points. With the help of our exam materials, you don't need to attend other expensive training courses and just need to take 20-30 hours to grasp our 070-177 exam questions and answers well.
After you purchased our BraindumpsQA's 070-177 exam materials, we offer you free update for one year. We will check the updates of exam materials every day. Once the materials updated, we will automatically free send the latest version to your mailbox.
In addition, we offer you free demo. Before you decide to buy our BraindumpsQA's 070-177 exam materials, you can try our free demo and download it. If it is useful to you, you can click the button 'add to cart' to finish your order.
070-177 Online Test Engine supports Windows / Mac / Android / iOS, etc., because it is the software based on WEB browser.
BraindumpsQA guarantees no help, full refund. If you fail the exam, you just need to send the scanning copy of your examination report card to us. After confirming, we will quickly give you FULL REFUND of your purchasing fees.
Easy and convenient way to buy: Just two steps to complete your purchase, we will send the 070-177 braindumps to your mailbox quickly, later you can check your email and download the attachment.
Microsoft TS: Microsoft Project Server 2010, Configuring Sample Questions:
1. You are upgrading from Project Server 2007 to Project Server 2010. You need to ensure that only Project Professional 2010 client computers can connect to Project Server 2010. What should you do?
A) Disable the Log on to Project Server from Project Professional option in Project Web Access (PWA) 2010.
B) Disable the Project 2007 Compatibility Mode option in Project Web Access (PWA) 2010.
C) Set the When starting option in Project Professional 2010 to Manually control connection state for client computers that are connecting to Project Server 2010.
D) Set the Task Mode setting in Project Web App (PWA) 2010 to Automatically Scheduled.
2. You have a Project Server 2010 environment. You need to assign a project to the Help Desk resources and allow these resources to self-assign which tasks to work on. What should you do?
A) Create a department named Help Desk. Assign the Help Desk resources to that department. Then publish the project to that department.
B) Create and populate the Team Name Lookup Table with the name of the Help Desk team. Assign the Help Desk resources to that team. Then assign all tasks to a Team Assignment Pool resource for that team.
C) Create a department named Help Desk. Assign a generic resource to that department. Then change all the Assignment Owner fields for the Help Desk resources to that generic resource.
D) Create and populate the Team Name Lookup Table with the name of the Help Desk team. Assign a generic resource as the Team Assignment Pool resource for that team. Then change all the Assignment Owner fields for the Help Desk resources to that generic resource.
3. You have a Project Server 2010 environment. Project managers are receiving task updates from resources in several different formats such as percent of work complete, actual work done, and hours of work done per period. You need to ensure that all resources report task status in the same format. What should you do?
A) Enforce a single progress reporting method.
B) Enable Single Entry mode.
C) Disable the Allow users to define custom periods for task updates option.
D) Edit the My Tasks view.
4. You have a Project Server 2010 environment with Microsoft SQL Server 2008 Analysis Services installed. You need to enable Project Server reporting. You start the Excel Services Web Service Application. Which application should you start next?
A) Security Token Service
B) Business Data Connectivity Service
C) Access Services Web Service
D) Secure Store Service
5. You have a Project Server 2010 environment. You need to enable the project manager to allow Resource A to report time for Resource B, while Resource B is on leave. What should you do?
A) Enable the Can be Delegate setting for the project manager.
B) Enable the Manage My Resource Delegates setting for the project manager.
C) Enable the Self-assign team task setting for the project manager.
D) Enable the Manage My Delegates setting for the project manager.
Solutions:
Question # 1 Answer: B | Question # 2 Answer: B | Question # 3 Answer: A | Question # 4 Answer: D | Question # 5 Answer: B |