Question 20: In a project that is published to Microsoft Office Project Server 2007, each task has both a generic
resource and a matching proposed named resource assigned. You receive approval to use these named
resources for the proposed assignments. You need to commit the named resources in your plan as
replacements for the generic resources. What should you do?
A. Change the booking type of the named resources from Proposed to Committed, remove the generic
resources, and then publish the plan.
B. Change the booking type of the generic resources from Proposed to Committed, change the booking
type of the named resources from Proposed to Committed, and then publish the plan.
C. Change the booking type of the generic resources from Proposed to Committed, replace them with
named resources, and then publish the plan.
D. Add the named resources to your plan, using a booking type of Committed.
Correct Answer: A