Question 2: Scenario 2 Your organisation is a large media services corporation (MSC). MSC uses Agile
development, within a Scrum framework. Here, the iterations are referred to as Sprints. For each Sprint, a
set of user-stories is defined, built, and tested. The user-stories are typically 1-2 lines long, indicating
what the customer wants the system to do. MSC is in the process of updating its website to meet the
recently introduced accessibility rules for websites. Accessibility means the availability of a system
suitable to members of the public with, for example, visual or hearing difficulties. It has been decided to
start with two requirements, as its first 2 Sprints: 1)Presentation of content with clear headings, short
sentences, text versions always available. 2)Consistent navigation through the website. You are the test
manager and there are four developers and two testers. You have all worked together previously, and are
very experienced in MSCs products. Although the accessibility rules are new to you and the team, you
have all attended a workshop where they were explained. Which of the following are product risks and
which are project risks? a.The navigation through some parts of the website may need to be different from
others. b.Sprint 1 may not be completed on time, leading to a delay to the start of Sprint 2. c.Text versions
of images may not always be possible. d.There may be a need to buy a capture-replay tool for regression
testing. e.A key member of the team may leave before the Sprints have been completed.
A.a, b and c are product risks, d and e are project risks.
B.a and c are products risks, b, d and e are project risks.
C.b, c and e are product risks, a and d are project risks.
D.a, d and e are product risks, b and c are project risks.
Correct Answer:B