1Z1-466 Free Dumps Study Materials
Question 9: What is not true about planning in OUM?
A. OUM has been developed with the intent that the approach for a given project be built up from a
core set of activities.
B. Projects should be tailored down from the full OUM work breakdown structures.
C. OUM takes an iterative and incremental approach to planning a project.
D. Tasks within OUM are considered place holders for work.
Correct Answer: D
Explanation:
Incorrect: Not A:OUM is designed to support a broad range of project types. As such, it must be
flexible andscalable. The appropriate point of balance for a given project will vary based on a
number of project risk and scale factors. The method has been developed with the intent that the
approach for a given project be "built up" from a core set of activities to implement an appropriate
level of discipline, rather than "tailored down".
Not C:OUM recognizes the advantages of an iterative and incremental approach to development
and deployment of information systems. Any of the tasks within OUM may be iterated. Whether or
not to iterate, as well as the number of iterations, varies. Tasks may be iterated to increase quality of
the work products to a desired level, to add sufficient level of detail, or to refine and expand the
work products on the basis of user feedback.