Question 19: A process analyst has performed simu-lation upon a business process and is analyzing resource
allocation within the process. The average elapsed duration for the process is 2 hours, 57 minutes. After
running the Process Resource Dynamic Analysis Report, it is observed that the Field Tech Resource has
an average Quantity Allocated value of .6 units. The Process Resource Allocation Dynamic Analysis
Report is also generated against the simu-lation results, and it is determined that there is an Average
Shortage Duration of 37 minutes, 30 seconds for the resource. The process analyst also observes that
the Field Tech Resource has been defined to the process as a bulk resource with an availability value of 3.
Based on this information, what conclusions can the process analyst draw?
A. There is at least one case in the business process that does not allocate the Field Tech Resource. The
pool of available Field Tech Resources can be reduced to 1 to eliminate resources that are never
allocated to the process. This will not affect the Average Shortage Duration value.
B. There are too many Field Tech Resources available to the process, as the sum of all Field Tech
Resource allocations to activities in the process divided by the total number of process instances is less
than one. This indicates that some Field Tech Resources are never allocated the business process.
C. There is at least one case in the business process that does not allocate the Field Tech Resource,
however there are also multiple concurrent process instances that are allocating the resource
concurrently and are competing for the resource. The pool of available Field Tech Resources can be
increased to reduce the Average Shortage Duration and the Average Quantity Allocated would increase to
a value close to 1.0 units.
D. There is at least one case in the business process that does not allocate the Field Tech Resource,
however there are also multiple concurrent process instances that are allocating the resource
concurrently and are competing for the resource. The pool of available Field Tech Resources can be
increased to reduce the Average Shortage Duration and the Average Quantity Allocated would remain the
same in subsequent simula-tions.
Correct Answer: D