Question 20: Refer to the exhibit
The following test cases need to be run, but time is limited, and it is possible that not all will be
completed before the end of the test window
The first activity is to run any re-tests, followed by the regression test script. Users have supplied
their priority order to tests.
Which of the following gives an appropriate test execution schedule, taking account of the
prioritisation and other constraints? [K3]
A. b, c, g, d, e, i, a, f, h
B. a, c, d, b, g, e, i, f, h
C. c, a, d, b, e, g, i, h, f
D. d, c, a, e, b, g, i, f, h
Correct Answer: C