C2090-421 Free Dumps Study Materials
Question 1: You are responsible for the projects Source Code Repository. When a developer notifies you
that changes are ready to deploy you must first check them in. You will use the Information Server
Source Code integration features to check in the changed assets. How will you identify the
DataStage assets the developer modified in order to send them to the workspace?
A. From the Information Server Manager Select the project then right-click on Synchronize with
source code control system.
B. Use Designer client Advanced Find,specify a modification date and the developer's username in
the Modified by fields.
C. From Information Server Manager use Search with advanced options,specify a date modified and
the developer's user name in the Modified by fields.
D. From the workspace perspective select the project Right-click then Refresh from
repository,specify a modification date and the developer's username in the Modified by fields.
Correct Answer: C