Question 17: The purchasing manager of ABC Corp., needs to procure aluminum sheets. The purchasing
manager wants to default supplier, site, and source document information on the requisition.
The purchasing manager creates an approved supplier list and sourcing rule, but does not associate
any source document in the approved supplier list.
A global agreement, a quotation, a request for quotation (RFQ) and blanket agreement exist for this
item.
The purchasing manager sets the "PO: Automatic Document Sourcing" to Yes.
The supplier and supplier site information are as follows:
GLOBAL AGREEMENT :SUPPLIER A SITE1
QUOTATION :SUPPLIER A SITE2
RFQ :SUPPLIER B SITE1
BLANKET AGREEMENT :SUPPLIER B SITE2
Which supplier and supplier site would default on the requisition?
A. SUPPLIER A, SITE2
B. No supplier or site information would be populated.
C. SUPPLIER A, SITE1
D. SUPPLIER B, SITE2
E. SUPPLIER B, SITE1
Correct Answer: D